DIRECTIONS:
Refer to panel manufacturers
specific recommendations. Condition the area to be installed,
adhesive and FRP panels at 65°F (18°C) or above
for 48 hours before, during and 48 hours after installation.
This adhesive should not be used in situations where
odors may be transmitted to foodstuffs. When installing
FRP to ceilings, follow the manufacturers recommendations
and use permanent mechanical fasteners in conjunction
with adhesive. When installing FRP over below-grade
concrete or block walls where moisture can penetrate
from the back, attach furring strips with mechanical
fasteners and adhesive. Then adhere panels using solid
backing if needed.
- Stir
any liquid on the surface into the adhesive.
- Cut
and pre-fit panels. Lay panels flat and let them acclimate
to room temperature for 12-24 hours before installing.
- Full
spread adhesive over entire surface using recommended
trowel. Do not leave bare spots. Press down firmly
on the spreader so that adhesive does not remain between
ridges.
- Place
panel against subsurface immediately. Press firmly
over entire surface working from center to edges so
that entire back of panel is in full contact with
backing.
- For
channel moldings and for permanent fasteners, follow
the panel manufacturers recommendations. Do
not fit panels too tightly into moldings. A minimum
1/16" expansion space is needed.
|
Application
|
Recommended
Trowel
|
Coverage
|
| FRP
Panel |
|

50-60 sq. ft/gal
|
Click
on the icons above to calculate the amount of product
you need!
CLEANUP:
- Wet
Adhesive: Clean, white
cloth dampened with soapy water.
- Dried
Adhesive: Clean, white
cloth dampened with mineral spirits; carefully following
warnings on the container.
WARNINGS:
Carefully read and follow all cautions and warnings
on the product label. Refer to the Material
Safety Data Sheet for additional product information.
|